Construction Updates 1/12/2024

1/12/2024: Work accomplished this week…
North Wing

  • Continued MEP rough-ins throughout.
  • Continued insulating walls and ceilings within units and along corridors on third and fourth floors.
  • Continued hanging and finishing drywall within units and along corridors on second, third, and fourth floors.
  • Continued installation of exterior vinyl and stone veneer siding.
  • Continued priming and painting walls/ceilings within units on first and second floor.
  • Continued installation of resident unit casework.
  • Completed pouring gypcrete underlayment on second floor.
  • Began installation of main water line along first floor corridor.

South Wing

  • Continued MEP rough-ins throughout.
  • Continue installation of patio doors.

Commons

  • Continued finishing drywall within formal dining room and bar area.
  • Began installation of resinous flooring within kitchen areas.
  • Completed installation of ceiling grid within formal dining room.
  • Completed installation of new beer cooler.
  • Continued MEP rough-ins within bar area.
  • Continued priming and painting walls and ceilings within formal dining room.
  • Completed installation of plumbing fixtures within bathrooms.
  • Completed foundational waterproofing on new IL apartment connector.