Construction Updates 1/5/2024

1/5/2024: Work accomplished this week…
North Wing

  • Continued MEP rough-ins throughout.
  • Continued insulating walls and ceilings within units and along corridors on third floor.
  • Continued hanging and finishing drywall within units and along corridors on second and third floors.
  • Continued installation of exterior vinyl and stone veneer siding.
  • Continue priming walls/ceilings within units for paint application.
  • Began installation of resident unit casework.

South Wing

  • Completed installation of roofing systems.
  • Continued MEP rough-ins throughout.
  • Completed framing balconies and installing Duxxbak decking.
  • Began installation of patio doors.

Commons

  • Continued finishing drywall within formal dining room and bar area.
  • Began installation of FRP walls within kitchen area.
  • Continued MEP rough-ins within bar area.
  • Began priming and painting walls and ceilings within formal dining room.
  • Continued installation of plumbing fixtures within bathrooms.
  • Completed installation of toilet partitions and bathroom accessories.
  • Completed placing concrete walls and began installation of structural steel at new IL apartment connector.