Construction Updates 2/9/2024

2/9/2024: Work accomplished this week…
North Wing

  • Continued MEP rough-ins throughout.
  • Continued hanging and finishing drywall and framing soffits on upper floors.
  • Continued priming and painting walls/ceilings within units on second and third floors.
  • Continued MEP finishes within first floor units.
  • Continued installation of resident unit casework, pre-hung doors, and trim within second and third floor units.
  • Continued installation of exterior façade.
  • Continued laying flooring within first floor units.
  • Set rooftop mechanical equipment.
  • Installed window blinds within first floor units.
  • Poured fourth floor gypcrete underlayment.
  • Began installation of balcony railings.

South Wing

  • Began insulating walls and ceilings on fourth and third floors.
  • Began hanging and finishing drywall on fourth floor.
  • Continued MEP rough-ins throughout.
  • Formed and poured concrete footers/walls for new connector to Commons building.

Commons

  • Continued finishing drywall ceiling within formal dining room and bar area.
  • Continued installation of MEP finishes.
  • Continued installation of food service equipment.
  • Began final coating walls and ceilings.
  • Completed CMU block at IL apartment connector.
  • Completed installation of millwork outside of men’s and women’s bathrooms.
  • Completed repair work within Bedford connector.