3/15/2024: Work accomplished this week…

North Wing

  • Continued MEP rough-ins on upper floors.
  • Continued finishing drywall within first floor common space and along first floor corridor ceilings.
  • Continued priming and painting walls/ceilings within units on upper floors.
  • Continued MEP finishes within second and third floor units.
  • Continued installation of resident unit casework, pre-hung doors, and trim within third and fourth floor units.
  • Continued setting countertops on third floor.
  • Continued installation of exterior façade.
  • Continued laying flooring within second and third floor units.
  • Continued installation of balcony railings.
  • Continued installation of metal roof at east side entry pavilion.
  • Began installation of elevators.

South Wing

  • Continued hanging and finishing drywall throughout.
  • Continued MEP rough-ins throughout.
  • Continued installation of balcony railings.
  • Began setting structural steel for new Common’s Building connector.
  • Began setting switchgear and exterior transformer vault.

Commons

  • Continued installation of MEP finishes.
  • Continued installation of food service equipment and casework.
  • Completed installation of exhaust fan duct to expo kitchen hood.
  • Continued setting roof trusses for new IL apartment connector.
  • Began hanging drywall ceiling in Fullenbach Room and at Captain’s table.
  • Began installation of bar area ceramic tile.

 