3/22/2024: Work accomplished this week…
North Wing
- Continued MEP rough-ins on upper floors.
- Continued finishing drywall within first floor common space and along first floor corridor ceilings.
- Continued priming and painting walls/ceilings within units on upper floors.
- Continued MEP finishes within second and third floor units.
- Continued installation of resident unit casework, countertops, pre-hung doors, and trim within third and fourth floor units.
- Continued laying flooring on upper floors.
- Continued installation of balcony railings.
- Continued installation of metal roof at east side entry pavilion.
South Wing
- Continued hanging and finishing drywall throughout.
- Continued MEP rough-ins throughout.
- Continued installation of balcony railings.
- Completed setting structural steel and began framing/sheathing new Common’s Building connector.
- Continued installation of switchgear and pulling wire to sub panels.
- Began installation of pre-hung doors and trim within third and fourth floor units.
- Poured gypcrete on second floor.
Commons
- Continued installation of MEP finishes.
- Continued installation of food service equipment and casework.
- Completed setting roof trusses and began installing roofing system for new IL apartment connector.
- Completed hanging drywall ceiling in Fullenbach Room and at Captain’s table.
- Began priming and painting ceilings within Fullenbach room and at Captain’s table.
- Began framing walls and soffits in IL apartment connector.
- Continued installation of bar area ceramic tile.
- Installed ACT grid in expo kitchen.
- Completed installation of dishwasher exhaust fan.
- Began priming and painting metal doors and frames.