Construction Updates 3/29/2024

3/29/2024: Work accomplished this week…
North Wing

  • Continued MEP rough-ins on upper floors.
  • Completed finishing drywall within first floor corridor and commons spaces.
  • Began framing, hanging, and finishing drywall soffits along corridors on upper floors.
  • Continued priming and painting walls/ceilings within units on upper floors.
  • Continued MEP finishes within second and third floor units.
  • Continued installation of resident unit casework, countertops, pre-hung doors, and trim within third and fourth floor units.
  • Continued laying flooring on upper floors.
  • Continued installation of balcony railings.
  • Continued installation of metal roof at east side entry pavilion.
  • Began installation of west side elevator.

South Wing

  • Continued hanging and finishing drywall throughout.
  • Continued MEP rough-ins throughout.
  • Continued installation of balcony railings.
  • Completed framing, sheathing and installation of windows at new IL Apartment connector.
  • Completed installation of switchgear and continued pulling wire to sub panels.
  • Continued installation of pre-hung doors and trim within second, third, and fourth floor units.

Commons

  • Continued installation of MEP finishes.
  • Continued installation of food service equipment and casework.
  • Completed installation of roofing system and framing walls/soffits for new IL apartment connector.
  • Completed priming and painting ceilings within Fullenbach room and at Captain’s table.
  • Completed MEP rough-ins within new IL apartment connector.
  • Completed installation of bar ceramic tile.
  • Continued priming and painting metal doors and frames.
  • Began installation of acoustical panel ceilings.
  • Completed waterproofing exterior of new IL apartment connector.
  • Began installation of millwork finishes in Fullenbach Room.