Work Accomplished This Week…

North Wing

  • Continued MEP rough-ins on upper floors.
  • Continued finishing drywall soffits along corridors.
  • Continued priming and painting walls/ceilings within units and corridors.
  • Continued MEP finishes within third and fourth floor units.
  • Continued installation of resident unit casework, countertops, pre-hung doors, and trim within third and fourth floor units.
  • Continued laying flooring on third and fourth floors.
  • Completed installation of metal roof at east side entry pavilion.
  • Completed installation of west side elevator.
  • Continued installation of balcony railings.
  • Began installation of ceiling grid on first floor corridor.
  • Began priming and painting west side stairwell.
  • Began installation of west side storefront entrances.

 

South Wing

  • Continued hanging and finishing drywall throughout.
  • Continued MEP rough-ins throughout.
  • Continued installation of balcony railings.
  • Continued pulling wire to sub panels.
  • Continued installation of pre-hung doors and trim within second, third, and fourth floor units.
  • Began forming exterior concrete generator pad.

 

Work Scheduled for Next Week…

North Wing

  • Continue MEP rough-ins throughout.
  • Continue finishing drywall soffits along corridors.
  • Continue priming and painting walls/ceilings within units and corridors.
  • Continue MEP finishes within third and fourth floor units.
  • Continue installation of resident unit casework, countertops, pre-hung doors, and trim within third and fourth floor units.
  • Continue laying flooring on third and fourth floors.
  • Begin installation of east side elevator.
  • Complete installation of west side storefront entrances.

South Wing

  • Continue hanging and finishing drywall throughout.
  • Continue MEP rough-ins throughout.
  • Continue installation of balcony railings.
  • Continue pulling wire to sub panels.
  • Continue installation of pre-hung doors and trim within second, third and fourth floor units.
  • Pour exterior concrete generator pad.