Construction Updates 4/12/2024

4/12/2024:

Work Accomplished This Week…

North Wing

  • Continued MEP rough-ins on upper floors.
  • Continued priming and painting walls/ceilings within units
    and corridors.
  • Continued MEP finishes within third and fourth floor units.
  • Continued installation of resident unit casework and
    countertops within third and fourth floor units.
  • Continued laying flooring on fourth floor.
  • Continued installation of west side elevator.
  • Began installation of ceiling grid on second floor corridor.
  • Completed priming and painting west side stairwell.
  • Completed installation of west side storefront entrances.
  • Began installation of corridor pilaster panels on second floor.

 

South Wing

  • Continued hanging and finishing drywall throughout.
  • Began priming and painting walls/ceilings within units and
    corridors.
  • Continued MEP rough-ins throughout.
  • Continued installation of pre-hung doors trim, casework, and
    countertops within units.
  • Set sprinkler pump and exterior building generators.
  • Completed hanging drywall along connector to Commons
    Building.
  • Began pouring curb line on east side parking lot.

 

Work Scheduled for Next Week…

North Wing

  • Continue MEP rough-ins throughout.
  • Continue priming and painting walls/ceilings within units and
    corridors.
  • Continue MEP finishes within third and fourth floor units.
  • Continued installation of resident unit casework and
    countertops within third and fourth floor units.
  • Continue laying flooring on fourth floor.
  • Continue installation of west side elevator.
  • Continue installation of corridor pilaster panels on second
    floor.
  • Begin installation of ceiling grid on third floor corridor.
  • Complete installation of corridor pilaster panels on second
    floor.

South Wing

  • Continue hanging and finishing drywall throughout.
  • Continue priming and painting walls/ceilings within units and
    corridors.
  • Continue MEP rough-ins throughout.
  • Continue installation of pre-hung doors trim, casework, and
    countertops within units.
  • Continue pouring curb line around exterior of building.