Construction Updates 4/24/2024

Work Accomplished This Week…

North Wing

  • Continued priming and painting walls/ceilings within units
    and corridors.
  • Continued MEP finishes within fourth floor units.
  • Continued installation of MEP finishes in corridors.
  • Continued installation of resident unit casework and countertops within fourth floor units.
  • Continued laying flooring on fourth floor.
  • Completed installation of west side elevator
  • Continued installation of east side elevator.
  • Completed installation of ceiling grid on all floors and began dropping ceiling tiles on fourth floor.
  • Continued installation of corridor pilaster panels, chair rail, and handrail.
  • Continued grading, pouring sidewalk, & installing site
    lighting.

South Wing

  • Continued finishing drywall throughout.
  • Continued priming and painting walls/ceilings within units and corridors.
  • Continued MEP rough-ins throughout.
  • Completed installation of ceiling grid on upper floors.
  • Began installation of MEP finishes within units and corridors.
  • Continued installation of pre-hung doors trim, casework, and countertops within units.
  • Poured epoxy flooring within resident storage room.
  • Turned on domestic water throughout.

Work Scheduled for Next Week

North Wing

  • Continue priming and painting walls/ceilings within units and corridors.
  • Continue MEP finishes within fourth floor units and corridors.
  • Continue installation of resident unit casework and countertops within fourth floor units.
  • Complete laying flooring on fourth floor.
  • Continue installation of east side elevator.
  • Continue installation of corridor pilasters panels, chair rail, and handrail.
  • Continue grading, pouring sidewalk, & installing site lighting.

South Wing

  • Continue finishing drywall throughout.
  • Continue priming and painting walls/ceilings within units and corridors.
  • Continue MEP rough-ins throughout.
  • Continue installation of MEP finishes within units and corridors.
  • Continue installation of pre-hung doors trim, casework, and countertops within units.
Loading...