Work Accomplished This Week…

North Wing

  • Continued painting walls/ceilings within units and corridors.
    and corridors.
  • Continued MEP finishes within fourth floor units.
  • Continued installation of MEP finishes in corridors.
  • Continued installation of resident unit casework and countertops within fourth floor units.
  • Continued laying flooring on fourth floor.
  • Continued installation of east side elevator.
  • Continued installation of corridor pilaster panels, chair rail, and handrail.
  • Continued grading, pouring sidewalk, & installing site lighting.

South Wing

  • Continued finishing drywall throughout.
  • Continued priming and painting walls/ceilings within units and corridors.
  • Continued MEP rough-ins throughout.
  • Continue installation of MEP finishes within units and corridors.
  • Continued installation of casework and countertops.
  • Continued installation of exterior façade at new connector.

 
 
Work Scheduled for Next Week

North Wing

  • Continue priming and painting walls/ceilings within units and corridors.
  • Complete MEP finishes within fourth floor units.
  • Continue installation of MEP finishes in corridors.
  • Complete installation of resident unit casework and countertops within fourth floor units
  • Complete laying flooring on fourth floor.
  • Continue installation of east side elevator.
  • Continue installation of corridor pilasters panels, chair rail, and handrail.
  • Continue grading, pouring sidewalk, and installing site lighting.

South Wing

  • Continue finishing drywall throughout.
  • Continue priming and painting walls/ceilings within units and corridors.
  • Continue MEP rough-ins throughout.
  • Continue installation of MEP finishes within units and corridors.
  • Continue installation of casework and countertops.
  • Begin installation of resident storage units.
  • Complete installation of exterior façade at new connector.