Construction Updates 5/10/2024

Work Accomplished This Week…

North Wing

  • Continued painting walls/ceilings within units and corridors.
    and corridors.
  • Continued installation of MEP finishes in corridors and fourth floor units.
  • Continued installation of resident unit countertops within fourth floor units.
  • Completed laying flooring on fourth floor units.
  • Continued installation of east side elevator.
  • Continued installation of corridor pilaster panels, chair rail, and handrail.
  • Began architectural and owner punchlist within units.
  • Began laying sod around perimeter of building.
  • Began installing elevator door smoke containment system.

South Wing

  • Continued finishing drywall throughout.
  • Continued priming and painting walls/ceilings within units and corridors.
  • Continued MEP rough-ins throughout.
  • Continued installation of MEP finishes within units and corridors.
  • Continued installation of resident unit casework and countertops.
  • Completed installation of exterior façade at new connector.
  • Completed installation of resident storage units.

Work Scheduled for Next Week

North Wing

  • Continue priming and painting walls/ceilings within units and corridors.
  • Complete installation of MEP finishes in corridors and fourth floor units.
  • Complete installation of resident unit countertops within fourth floor units.
  • Continue installation of east side elevator.
  • Continue installation of corridor pilasters panels, chair rail, and handrail.
  • Continue architectural and owner punchlist within units.
  • Continue laying sod around perimeter of building.
  • Complete installing elevator door smoke containment system.

South Wing

  • Continue finishing drywall throughout.
  • Continue priming and painting walls/ceilings within units and corridors.
  • Continue MEP rough-ins throughout.
  • Continue installation of MEP finishes within units and corridors.
  • Continue installation of resident unit casework and countertops.