Construction Updates 5/24/2024

Work Accomplished This Week…

North Wing

  • Continued painting walls/ceilings within common spaces.
  • Continued installation of MEP finishes within first floor commons spaces.
  • Continued WCC, architectural, and owner punchlist throughout.
  • Completed laying sod around perimeter of building.
  • Completed installation of wood slat ceiling outside of elevators.
  • Began installation of flooring within corridors and commons spaces.
  • Began paving east side parking lot.

South Wing

  • Continued finishing drywall throughout.
  • Continued priming and painting walls/ceilings within first floor units and corridors.
  • Began WCC punchlist within units and corridors.
  • Completed MEP rough-ins throughout.
  • Continued installation of MEP finishes within first units and corridors.
  • Completed installation of resident unit casework.
  • Continued installation of corridor pilaster panels, chair rail, and handrail.
  • Set transformer and began process to obtain permanent power to building.

Work Scheduled for Next Week

North Wing

  • Complete priming and painting walls/ceilings within common spaces.
  • Complete installation of MEP finishes within first floor commons spaces.
  • Continue WCC, architectural, and owner punchlist throughout.
  • Complete installation of flooring within corridors and commons spaces.
  • Begin striping both west and east side parking lots.

South Wing

  • Complete priming and painting walls/ceilings within first units and corridors.
  • Complete installation of MEP finishes within first units and corridors.
  • Continue installation of corridor pilasters panels, chair rail, and handrail.
  • Continue WCC, architectural, and owner punchlist within units and corridors.
  • Obtain permanent power to building